A new report, Britain's Biggest Opportunity, by Bitcoin Policy Institute's Conner Brown and Xapo Bank's Joey Garcia, proposes putting Bitcoin miners behind the transmission bottlenecks where Scottish wind generation is already being curtailed. The miners would buy power that cannot currently be moved south. It is a specific proposal, not a claim that mining can eliminate Britain's constraint bill.
I have argued for years that Scotland should consider converting surplus wind into an asset held for the Scottish people, rather than paying to suppress generation. The report does not make my public ownership argument. It does, however, describe a mechanism worth testing, cite evidence for flexible demand, and acknowledge what still needs to be modelled.
This follows my earlier analysis of energy transition and ownership. The question is whether a new customer located at the bottleneck can make productive use of electricity that otherwise goes nowhere.
What the proposal actually says
A conventional hyperscale data centre needs firm, uninterrupted power and extensive supporting infrastructure. Bitcoin mining is more modular and can be switched off when the grid needs the power elsewhere. The report cites research on ten mining companies whose facilities curtailed their consumption between 5% and 31% of the time in response to grid conditions. That is evidence of flexibility, although it does not prove the economics of any particular Scottish site.
The authors ask the Department for Energy Security and Net Zero and the National Energy System Operator (NESO) to assess mining behind transmission bottlenecks, especially near the Scotland–England boundary. They expressly warn that the total constraint bill is not the amount mining could save. Consumer savings, emissions and infrastructure costs would all need project-level modelling.
Separate the costs
The National Audit Office reported that grid constraint costs reached £1.9 billion in 2025–26 and could rise as high as £7.8 billion by 2030 without concerted action. These are whole-system costs. They include paying generators to reduce output and paying others, often gas plants, to replace it. They are not simply the payments made to wind farms to turn down.
The NAO also found that 64 of 80 grid projects identified in NESO's 2024 Clean Power advice were ongoing, most at an early stage, and that three projects marked for acceleration had shown no significant acceleration. Ofgem estimated £70 billion of grid investment between 2025 and 2031. Grid construction remains the essential long-term answer; flexible local demand could potentially reduce waste while that work proceeds.
Figures quoted for Scottish wind turn-down payments and replacement generation cover different periods and different cost categories. Putting them side by side as if they were interchangeable would overstate the case. The relevant test is how much constraint cost a mine at a specified location and operating schedule could actually avoid, net of its own capital and operating costs.
What might it be worth?
The honest answer is that nobody can yet give a credible national savings figure. A mining project needs access to sufficiently frequent low-cost curtailed power, an acceptable connection, equipment and cooling, a commercial contract, and a Bitcoin price at which operation makes sense. A machine that runs only occasionally may absorb waste but struggle to repay its capital cost. If it operates when the grid is unconstrained, the environmental and consumer case changes.
My view is that a well-designed programme could create substantial Scottish value over time, but my earlier suggestion of “billions a year” should be treated as an ambition to test, not a forecast. The report does not establish such a figure. A public assessment should publish the assumptions, counterfactual costs and sensitivity to Bitcoin prices before any treasury benefit is claimed.
Who owns the coins?
The report's unanswered question is who receives the asset created. Under a purely private model, miners and their financiers capture the mining return while the public may benefit only indirectly through lower system costs, local taxes or contracts. That might still be worthwhile. But if public support, land, connections or curtailed renewable output are involved, Scotland should ask what public stake or revenue share is justified.
Scotland Reimagined's energy proposals argue for capturing a public return from energy resources and directing it towards renewables and household costs. The same principle can be applied here, subject to legal powers, commercial viability and public scrutiny. A public Bitcoin reserve is one possible structure, not a substitute for deciding whether the underlying project benefits consumers.
The American contrast
In March 2025, Donald Trump signed an executive order establishing a US Strategic Bitcoin Reserve. It was initially capitalised with government Bitcoin obtained through forfeiture. The order directed officials to explore budget-neutral ways to acquire more; it did not announce open-market purchases. That distinction matters. The US example shows that governments are considering Bitcoin as a reserve asset, but does not prove Scotland should mine or hold it.
Four tests before a Scottish pilot
Price risk: Bitcoin's value can move sharply. A public body would need explicit rules for custody, sale, accumulation and loss limits. Selling output promptly and holding it in a reserve are very different policies.
Additionality and emissions: Modelling must compare mining with the actual alternative at each site: curtailed wind, storage, other flexible demand, grid reinforcement and replacement generation. A green label is not evidence of lower emissions.
Place and consent: Facilities need planning scrutiny, noise and cooling standards, and a clear account of local benefits. Communities should be consulted before sites are selected.
Market and legal access: Banking, procurement, public finance powers and secure custody are part of the project, not administrative details to settle afterwards.
What follows
DESNZ and NESO should publish a scoped assessment of flexible mining behind the relevant Scottish transmission boundaries, including consumer savings, emissions, capital costs and alternatives. Ownership terms should be decided before any public-backed site is announced. If a project proceeds, its success should be measured against a practical public outcome: lower total costs for households, with transparent accounting of who receives the additional value.
Britain has spent years paying some generators to stop and others to start. A flexible buyer at a constrained location may help. The engineering question needs independent modelling. The political question should be asked now: who owns what Scotland produces?
Sources and context
- CoinDesk report on Britain's Biggest Opportunity, 14 November 2026. The original institute report should be read alongside it when publicly available.
- National Audit Office, Upgrading the electricity transmission network, September 2026.
- NESO, The Balancing Act: Outturn, November 2026.
- US executive order on the Strategic Bitcoin Reserve, March 2025.
Further reading: Energy, place and power and Scottish political economy.